Rumah Tumbuh Wedomartani · Ngemplak, Sleman · 2020–2021 · Phase 1 built

Send Brief
Tampak muka tahap satu Rumah Tumbuh: satu lantai dengan teras dan taman yang sudah selesai, difoto lurus dari jalan pada cahaya siang.

Rumah Tumbuh Wedomartani, Ngemplak — phase 1, 2021. Photograph: studio photography collaborator.

House

Rumah Tumbuh Wedomartani

Ngemplak, Sleman, DIY · 2020–2021

Phase one was completed in 2021 and has been lived in since. The construction documents for phase two have been delivered and not yet built. The photographs on this page show phase one as it is, not an impression of the completed whole.

The site and the problem

The client had a plot of 7.5 by 20 metres and needed four bedrooms, but the budget covered about half of that. The route most often taken in this situation is to build the whole thing at reduced quality. The result is a house that is finished but leaking within three years.

A five-metre neighbourhood road on the south side, a three-metre setback, a two-storey height limit. Nothing about the site was difficult; what was difficult was the timescale — the family would live in phase one for five to eight years.

Gambar 01. The hatched area is phase one as it stands now; the dashed area is phase two above it. Both were drawn together in 2020.
Geser untuk melihat seluruhnya

Massing study

Three alternatives were tested against an unusual question: how does this house look during the five years before phase two arrives.

Alternative A— Ditolak

Rejected. A single full storey fits the budget but closes off any phase two without taking the roof off.

Alternative B— Terpilih

Selected. Phase one is single storey on a two-storey structure; phase two is drawn as a dashed line and built later without demolition.

Alternative C— Ditolak

Rejected. Building the whole area on one floor meets the brief but takes the green area to its limit and uses up the garden.

Design decisions

  1. 01

    The phase two structure was drawn and built during phase one

    Columns, foundations, and starter bars for the upper floor went in at the beginning. Adding them later means breaking out floor, roof, and part of the walls, at a far higher cost than installing them now.

    See drawing 08

  2. 02

    The phase one roof was designed to be taken down cleanly

    The light-gauge steel frame is bolted rather than welded, so it can be dismantled. The roof tiles can be reused in phase two.

    See drawing 09

  3. 03

    Pipe and cable routes for the upper floor are already cast in

    Including sleeves through the slab, water points, and cable runs terminating in closed boxes. No wall will need to be broken out later.

    See drawing 10

  4. 04

    Phase one still has to feel finished, not like a building on hold

    This is the decision most often skipped. Phase one was given a complete elevation, a finished veranda, and a finished garden.

    That family will live there for five to eight years, and five years is not a length of time worth spending inside a half-built house.

    See drawing 04

Working drawings

Plans, sections, and details from the working drawing set for this project. Annotations inside the drawings stay in Indonesian: the people reading them are on site.

Gambar 04. Phase one plan. The heavier columns are those already calculated for two storeys, with starter bars projecting above.
Geser untuk melihat seluruhnya
Gambar 05. Phase two plan, drawn alongside phase one in 2020. The phase two frontage sits 1.20 m behind phase one.
Geser untuk melihat seluruhnya
Gambar 06. Section E-E. What stands now is drawn solid; phase two is dashed. The starter bars are visible above the columns.
Geser untuk melihat seluruhnya
Gambar 07. Exploded axonometric. The last layer is dashed: it has not been built, and the drawing does not pretend otherwise.
Geser untuk melihat seluruhnya
Gambar 08. Starter bar detail. The protective PVC sleeve was added on site, not in the original drawing — see What changed on site.
Geser untuk melihat seluruhnya
Gambar 09. Two ways of connecting the roof frame. The left one is not used precisely because it has to be cut to be dismantled.
Geser untuk melihat seluruhnya
Gambar 10. Positions of the sleeves cast in during phase one. Their positions are recorded on the as-built drawings so that phase two does not have to search for them.
Geser untuk melihat seluruhnya
Gambar 11. Extract from sheet A-311. Revision R1 records the added protective sleeve, four weeks after the house was occupied.
Geser untuk melihat seluruhnya

Regulatory compliance

Regulatory compliance for Rumah Tumbuh Wedomartani
ParameterProvisionUsed
KDB (building coverage)max 60% (90 m²)72 m²
KLB (floor area ratio)max 1.20.48 in phase 1; 0.92 planned
KDH (green area)min 20%34%
GSB (front setback)3 m from plot boundary3 m
Heightmax 2 storeys1 storey built
PermitPBG for the two-storey schemeprocessed in 5 weeks

The provisions applied to this site in this year. Provisions differ between areas and can change. The abbreviations are the Indonesian regulatory terms and are kept as they are.

Permit processing time

5 weeks

Processing time at the authority is outside the studio’s control. We record the actual time for each project so that you have a real picture rather than a promise.

Existing condition

Construction

Dated progress photographs, in chronological order.

Built

The building in relation to the neighbourhood road and the neighbouring house to the west

What changed on site

The starter bars projecting above the phase one columns had to be protected while the house was occupied. A PVC sleeve that was not in the original drawing was added after the first week, and it entered the as-built drawings as revision R1.

The phase two frontage was set back 1.2 metres from the phase one frontage after an elevation study showed that without the setback, phase one would read as the part left behind rather than as a complete piece.

No project runs exactly as drawn.

Credits

Client
A young family whose budget covered only half the plan
Structural engineer
Independent practice, Yogyakarta
Contractor
Main contractor
Photographer
Studio photography collaborator

Have a plot with a similar problem? Send us a brief.

Send us the location, the plot area, and the rooms you need. We reply within two working days with an initial assessment — including if we think another practice would serve your project better.

We take on a maximum of six new design projects a year. Replies during working hours, Monday to Friday.